Back to Safety Alerts
|
U.S. Department of the
Interior
Minerals Management Service
Gulf of Mexico OCS Region
|
Safety Alert No. 230
3 May 2005 |
Contact:
Glenn Woltman
(504) 736-2438
|
Equipment Failure on Deepwater Rig While Running
Casing in Open Waters
During the deployment of the
22-inch surface casing in open water, an incident evolved resulting in the total
loss of casing with inner cement stinger and wellhead. This incident occurred
while the second stand of the 6-5/8 inch (drill pipe) landing string was being
picked up, with the upper end of the first stand of drill pipe hanging in the
rotary slips, and with the full weight of the entire string of 22-inch casing
and subsea wellhead below. The slips suddenly jumped twice. The second jump
apparently released the drill pipe from the slips and allowed the pipe with
inner string to fall through the rotary.
Weather conditions at the
time of the incident were reported to be benign. The acoustic doppler current
profiler monitoring system was not functioning. Information on limiting current
and wave environments versus the casing and landing string design criteria was
not available. No stand-down conditions had been predetermined. Weight
indicator information was not charted. Motion compensators on the rig were
rendered unusable, since the pipe had been set in the slips. The length of the
casing run exceeded the depth to the mudline, placing the end of the pipe below
the low-pressure wellhead housing.
Key information needed to
determine root cause(s) for the failure was not available. Conditions at the
time of the incident may have been marginal to land the casing assembly
successfully, given the sea state and the defined configuration of the drill
pipe and casing assembly.
Material and procedural
changes incorporating design margins made by the operator on the re-drill may
have allowed the operations to proceed without incident. Listed below are the
two significant operational changes made:
1.
Shortening the 22-inch casing length (end of casing above 26-inch housing
at the mudline), thus providing free end boundary conditions while running the
inner string.
2.
Changing the landing string for the 22-inch casing to a heavy wall drill
pipe and using a set of slips with a longer contact length
to increase slip-crushing capacity.
The MMS recommends:
§
Operators working in open waters
should consider stress analysis testing given defined configurations of the
casing assembly at varying sea states, with a thorough analysis of all dynamic
loads, including tripping loads and slip-crushing loads. Stand-down conditions
should be identified and discussed during the JSA.
§
Operators should require continuous
recording of hook loads on drilling rigs to capture data for trending analysis
during all open water drilling operations.
§
Per MMS NTL 2005-G05, Operators will
be required to measure loop currents to ensure all activities in open waters are
in line with the safe operating envelope determined from previous stress
analysis testing.
§
The slips and bowl should be
inspected for wear in accordance with API Spec 8A.
§
Visual, dimensional, and
flaw-detecting inspections should be performed on all handling tools, such as
bails, slips, master bushings, elevators, spiders, and top drive stem
assemblies, to verify load capacity. Elevators, spiders, and bails should be
pull tested to the maximum anticipated load in accordance with API Spec 8B / ISO
13534:2000. Reference is made to API Spec 8C, Specification for Drilling and
Production Hoisting Equipment (PSL 1 and PSL 2), third edition Addendum 1,
and to ASTM E4-03, Standard Practices for Force Verification of Testing
Machines.
A complete account of the
accident is available on the MMS website at
http://www.gomr.mms.gov/homepg/offshore/safety/acc_repo/2005-027.pdf
|