Erroneous Activation of Dump Valve Causes Loss of
165 bbls of Oil-Based Mud
During drilling operations,
drilling personnel working the pit room shifted an actuator handle that
controlled the degasser suction valve, according to the posted line schematic.
However, the rig immediately began losing mud. After about three minutes, the
actuator-controlled valve was shut.
An investigation discovered
that the actuator did not control the degasser suction valve as shown on the
line schematic, but was connected to the dump valve of the process tank. As a
result of the incident, 165 barrels of synthetic oil-based drilling fluid and
cuttings, including 96 barrels of oil, were lost overboard. It was also found
that no master dump valve was installed downstream of the individual compartment
dump valves and manifold.
The investigation found that
the piping/schematic error had been previously discovered during a separate
incident, but only a hand label, overwriting the integral label of the line
schematic, warned that the handle controlled the dump valve. The line schematic
itself was not corrected. The crews were previously instructed that the hand
label was correct and they were to ignore the piping diagram shown on the line
schematic. However, in the course of performing the operation, the drilling
personnel referred to the faulty line schematic and failed to notice the written
hand label correction beside the actuator handle.
The MMS recommends the
following to operators:
- Consider installing a
master dump valve downstream of the individual lines as a secondary barrier to
inadvertent fluid dumping. Several recent incidents involving the inadvertent
dumping of mud would have been prevented by this practice.
- Avoid temporary hookups
and hand labeling when line schematic variances are discovered. Correct the
plumbing and the schematics immediately so as to remove the possibility of
misinterpretation.