Shallow Gas Blowout and Rig Evacuation
Recently, a well was being
drilled from a producing platform. While making a short trip after penetrating
shallow formations, the operator experienced a sudden gas influx, causing the well to be
put into the diverter system. The uncontrolled flow subsequently caught fire,
resulting in abandonment of the rig and platform. Though the well bridged after
about ten minutes, damage to the rig and platform are estimated to be two million dollars.
It is thought that the gas was swabbed into the wellbore from a shallow sand that
had been logged as potentially productive in a previously drilled well. This zone
was not identified as a shallow-gas hazard in the well plan. The fire damage was
increased by a possible premature failure of the diverter system and subsequent exposure
of stored equipment to the uncontrolled flow and fire.
The MMS recommends the following
to operators preparing to drill a new well from a previously drilled surface location:
1.
Shallow-gas hazard studies prepared for
new wells from previously drilled surface locations should include a study of the old logs
as well as seismic data. Drilling operations should be explicitly warned of
shallow-gas deposits identified in previously drilled wells.
2.
Care should be taken in the design,
installation, and bracing of diverter systems to allow enough rigidity to resist flexing
failure and to allow uncontrolled flows to exit the system downwind and outboard of the
rig. Proper design, construction, and targeting to limit the direct impact of flow
upon pipe walls should be observed.
3.
Where possible, electric cable bundles
should be routed so as to be clear of the diverter system. Storage of flammable
supplies next to the diverter system should be restricted where possible.